We are upgrading the gas pipes along Windsor Road to ensure you continue to receive a reliable gas supply for many more years to come. Our aim is to replace all the metallic mains and service pipes in these locations. This means that we will need to excavate holes in the ground to access the gas pipes in order to inspect and replace them.

Start date: 21 August 2023
Duration: 18 weeks

We will be starting on the Oxford Road junction implementing our own four-way temporary lights, we expect these to be situ between 3-4 weeks as we progress down Windsor Road. Once we are far enough away from the junction to remove these, we will be using temporary traffic lights working down Windsor Road. These lights will be manned from 7am to 7pm to maintain the flow of traffic.