    Pipes that Require an Easement:

    • All mains in private land N.B. including ring/approach mains supplying risers for multiple occupancy buildings (MOB’s).
    • All services operating at pressures greater than 75 mbar (Low Pressure) in private land.
    • All services greater than or equal to 63mm diameter crossing Private Land not owned by the customer (i.e. “Third Party Land”)
    • All services greater than 50m in length in Private Land.
    • Mains and/or services to be installed within private roads/streets not dedicated to public use, that supplies a property that is NOT abutting the street i.e. Where statutory powers do not apply.
    • For all other services crossing Third Party Land (not covered by the rules above), Cadent will require a Consent to Lay form from the landowner to be obtained prior to installation and a copy sent to the Connections team and Land Services team along with any as laid plan for Cadent’s records.

    Get started

    Here you will find out more about the steps you need to take to register to make connections to our network and the various processes we need to follow with you. Don't worry, we’ll stay in touch along the way to make sure it's going smoothly and you’re happy with everything.


    • Register with us

      To lay gas infrastructure and transfer ownership to Cadent, or lay infrastructure on behalf of an IGT, you must register with us first.



    • Submit request

      Submit your request online via the IGT and UIP web portal, or manually via email. An administration charge applies to Fast Tracks and Quotations.


    • Validation and approval

      We will process your request in line with our policies and procedures. Based on your request, we will provide the details you need to progress your work.


    • Plan in works

      Once you have received design approval, you can plan in your works.


    • Works complete

      Once you have received clearance, you can complete your works. We may visit site to audit the works and ensure they are carried out safely and responsibly.


    • Submit completion file

      Send us your completion file no later than 14 days after completing the works.


    • Asset adoption letter issued

      Once we have validated your completion file, we will issue an asset adoption letter to confirm the project is complete.

    More information

    Escalation

    IGT / UIP submissions: Adam Smith 0797 385 9295 / Nic Evans 0781 372 0660 / Pete O’Neill 0778 590 6608
    Analysis: Monir Uddin 0787 050 4664 / Andrew Gilfeather 0797 181 4627
    Completions: Hannah Dakin-Stevens 0781 239 1187 / Lee Tedds 0797 041 9669

    Incident alert
    0!

    Incidents

    Phone

    Smell Gas?

    0800 111 999*

    Aa Accessibility