Redbridge

    Maintenance and upgrade works - Redbridge site

    Our facility in Redbridge has been operational since 1981, supplying gas to Redbridge and the wider surrounding area.

    As part of our ongoing commitment to maintain the gas supply, we need to carry out some works to our Redbridge site; these works will lengthen the life of this key asset and improve its security; this will enable us to continue to effectively meet peak gas demand across this area of London in the years to come. This programme of work has been developed by the Government’s Health and Safety Executive, the energy regulator Ofgem, and the Department of Energy Security and Net Zero.

    Allotment-Locations.jpg

    Proposed work:

    As part of our ongoing commitment to maintain the gas supply, we need to carry out some works to lengthen the life of this key asset and improve its security.

    The map provides a bird’s eye view of the existing site in Redbridge where we need to carry out the following maintenance and improvements:

    • Replacement of some equipment on our main Redbridge Lane West site including mechanical equipment and pipe support
    • Modification of smaller adjacent cadent site to replace ladders and platforms to make it safe for our personnel
    • Installation of fencing to improve the safety of the site and replacing perimeter fence with higher specification fencing.

    In order to facilitate this work, we need to:

    • Undertake some vegetation and tree removal
    • Install a temporary site compound for our construction team, including welfare facilities, storage for machinery and equipment, parking for HGVs and a main project office. This will be based at Redbridge Lane West Allotments.

    We will ensure all ecological surveys are complete prior to commencing work and we will replace every tree removed with five new trees. During construction, our team will use the latest technology to make our operations quieter for our neighbours and we will monitor noise levels throughout our activities. We are working alongside the Redbridge Neighbourhood Street Scene Team and a specialist consultant to ensure all work is undertaken safely.

    Pre and post view of our sites:
    Redbridge-Lane-West-allotments-map_existing.jpg
    Redbridge-Lane-West-allotments-map_after_1.jpg

    Our footprint of our site will change due to the works we need to carry out.

    View of site during construction

    Redbridge-Lane-West-(1)

    We have been in discussions with affected allotment holders over the past few years to see how their leases for the allotment areas will change. We have made relevant agreements with affected allotment holders as applicable to their specific needs. At Redbridge Lane West allotment, nine allotment holders were affected by our plans but the remaining allotment holders will not have to change their allotment plots.

    Maintenance and upgrade works – Redbridge site

    We have now completed all our engineering works at our Redbridge site, handing over the land owned by Redbridge Council, back to them. (The nine allotment areas) We will be off site by the end of next week (19/06/26).

    We would like to thank the allotment holders at Redbridge and the local community surrounding this site, for their continued patience and understanding whilst we completed this important and essential project.

    The project at Redbridge was one of the essential projects Cadent commited to upgrade and improve security to ensure we can effectively meet the peak gas demand across this area of London for many decades to come.

    Allotment holders

    For the (3) allotment holders wishing to return to their original allotment areas, Vision will be in touch with you directly to discuss the allotment area. Once this has been agreed, Cadent will liaise with these allotment holders and we will assist them in returning to the agreed area. We have been working with Vision over the past month to arrange this smooth transition. Any questions please speak to your Vision representative.

    Helping the community

    Throughout the works we have tried to be a good neighbour and help the local community too. Throughout the years as part of this project we have laid a new water supply to the Wanstead Park Road allotments, supplied Sprout There! with a new polytunnel covering when it was damaged in strong winds, provided new toilets at Redbridge allotments, repaired and reinstalled water butts at the Redbridge allotments, parking spaces and a hard surface for deliveries too. Most recently the team helped Uniting Friends by transforming one of their community garden spaces.

    Once again, a big thank you to the Redbridge Community.

    Work on the project is progressing well. We have a slight change to our timeline, instead of finishing work by the end of April we will now be off site by the end of June. Please see below some key highlights for the next few months.

    Timeline of final activities
    • The main construction works are complete, we have reduced our welfare area to reflect the smaller team we now have, to enable us to start reinstatement.
    • The work we are doing at the moment is finishing off those little ‘snags’ that need to be resolved on the main site now. This should be complete by the end of April.
    • We have some final ‘off site’ works to complete around the valve pit which is situated to the left-hand side of site (in the allotment area) this is still not 100% defined, but we expect it to take until the end of May.
    • The remaining effort is largely around landscaping and ‘making good’ the surrounding area, which we will be completing over Spring.
    • Once all this work is complete, we will start demobilising and reinstating. This will lead us to be off site by the end of June.

    We will be in touch with the individual allotment holders who wished to return to an original allotment plot closer to the end of the project.

    Thank you to all who were able to attend the information event in February.

    Please see the summary of the event, including the updated timeline.

    February-24-engagement-session_1

    Timeline-Feb-2024-(1).JPG

    Virtual Engagement Event

    Following our update in January regarding the Secretary of State approval, we want to update you on our construction timeline for the Redbridge Lane West Project.

    We would like to invite you to a virtual engagement event on Tuesday 27th February from 5-6:30pm.

    During this session we will present our update on the project and you will have the opportunity to ask questions in the same way as in the usual in-person sessions.

    If you wish to join us, please email us on: [email protected] or call us on 0800 068 7925 to confirm attendance and to receive further information.

    We look forward to speaking to you and answering any questions you may have about the project.

    Secretary of State approval received for Redbridge project

    We have now received the consent from the Secretary of State to be able to start our maintenance project at our site in Redbridge, which includes nine allotment areas.

    Redbridge London Borough Council received the consent from the Secretary of State in the new year and confirmed to Cadent that the approval had been received.

    With the Secret of State consent, we are now able to fully plan our timetable of works. We aim to share the outline timetable in the next few months.

    We will be holding a drop-in event on the Tuesday 28 November between 3 and 7pm at Wanstead Golf Club (Overton Drive, Wanstead, London E11 2LW).

    This will provide an opportunity for all local residents to learn more about the project and ask questions about the project with the team.

    Project-leaflet-11-23.pdf

    Redbridge Council have submitted the application to the Secretary of State and we await the decision.

    In the meantime we are preparing the construction programme and we will update you once the final programme has been decided.

    Production
    Go to current incident
    0!

    Incidents

    Telephone Icon - Contact Us

    Smell Gas?

    *
    Aa Accessibility