Scrubs Lane, Hammersmith

    Scrubs Lane and Du Cane Road, Hammersmith

    We’re upgrading the old metal gas pipes along Scrubs Lane and Du Cane Road, Hammersmith. These works will keep homes and businesses connected to a safe and reliable gas supply for cooking, heating and hot water, whilst reducing the likelihood of us having to come back to make repairs in the future.

    Work starts on Monday 13 October 2025 for ten weeks.

    The work will be carried out in four phases.

    Phase 1A and B

    Temporary traffic lights at the junctions with Wood Lane, Scrubs Lane and North Pole Road from 13 to 26 October 2025.

    Phase 1B

    As per Phase 1A from 27 October to 9 November 2025.

    N.B. Due to Highway Authority network requirements, the traffic management may need to be amended to include the full junction closure of North Pole Road at the junction of Scrubs/Wood Lane. Please check TfL’s website.

    Phase 2

    Southbound lane closure on Wood Lane from the junction of North Pole Road to the junction of Du Cane Road from 10 November to 19 December 2025.

    There will be junction closures off Wood Lane to Nascott Road and Glenroy Street. Access to these streets will be via Caverswall Street only from 10 November to 19 December 2025.

    Phase 3

    As per Phase 2 with the addition two-way temporary traffic lights on Du Cane Road from 1 to 12 December 2025.

    The traffic management will be monitored throughout these works to ensure traffic is flowing. Please visit insert TfL website for updates on the traffic management and diversions.

    Please plan extra time for your journeys.

    We are pleased to say that there are no planned gas supply interruptions.

    We’d like to reassure you that we’ll keep disruption to a minimum and get your streets back to normal as soon as we can.

    Thank you for your patience while we carry out these essential upgrades to ensure that you can continue to receive a safe and reliable gas supply, now and into the future.

    Map of Scrubs Lane, Hammersmith mains replacement works showing junction works and southbound lane closure.

    Diversion map for Scrubs Lane mains replacement works, Phase 2/3, showing closure and diversion route.

    BUS DIVERSION ROUTES

    Due to the southbound lane closure, we have worked with TfL and the local Highways Authorities to keep the traffic flowing and keep the bus routes going too.

    Please see bus diversion routes below.

    PHASE 1A & 1B

    Please check TfL’s website for updates. No diversions needed at this time.

    PHASE 2 & 3
    Routes 7, 70 and N7 towards East Acton, Chiswick Business Park and Northolt

    From Barlby Road junction with Highlever Road divert left Highlever Road, left St Quintin Avenue, right St Marks Road, right Cambridge Gardens, left Bramley Road, ahead St Anns Road, left Royal Crescent, right Holland Park Avenue, third exit Holland Park Roundabout to West Cross Route, A40 slip to Wood Lane.

    Route 220 towards Wandsworth

    From Wood Lane junction with North Pole Road left North Pole Road, ahead Quintin Gardens, right Highlever, left St Quintin Avenue, right St Marks Road, right Cambridge Gardens, left Bramley Road, ahead St Anns Road, left Royal Crescent, right Holland Park Avenue, second exit Holland Park Roundabout to Shepherds Bush Green to line of route.

    Production