You complete our initial enquiry form providing the following key information:
We perform a high level network analysis and mapping to assess whether a connection is possible.
We will talk to you about this once the Initial Enquiry has been completed.
There is no charge to you for this activity.
15 working days
Complete our application form to apply for a Detailed Analysis Study report (DAS). The DAS will provide you with;
£750 + VAT
Detailed Analysis Study 30 working days from receipt of payment
Following receipt of your signed agreement, you will be invoiced. Once we have received payment the study will be completed and issued within 30 working days.
The DAS is a snapshot of the network at the current time and is not a guarantee of gas flow as the dynamics of the gas distribution network are subject to change.
Once you have reviewed your study we can discuss the next steps with you or you can proceed to Application to Connect – Step 3, when you are ready.
If you want to proceed to connection simply complete and submit an application to connect - the template can be found below.
There are no costs associated to this activity.
We will validate and acknowledge receipt of your application form within two working days.
For all entry connections we will issue a connection offer that sets out both parties obligations for the onsite works associated with the installation of the injection facility and the physical entry connection onto the pipeline grid network. The connection offer is valid for 45 days.
There are no costs associated with us providing you with a connection offer
We aim to provide a Connection Offer within 2-3 weeks of reviewing your application.
You have completed the first four steps (Commercial Arrangements) in the process to getting connected and you now have a contractual agreement with us to inject biomethane into the network. The next 4 steps of the process are:
5.Initial meetings are held to discuss your proposal in more detail
6. We review and approve your design documents in order to allow works to begin
7. Site testing and commissioning happens here
8. Financial reconciliation and project close out.
We want to hear from you and work with you.
We want to make sure you can easily start injecting your gas into our network.
Email us at [email protected] or call 0781 614 5573