• Apply

    Either fill in our online application form, or give us a call and we’ll work through your application with you.

  • Initial preparation

    Decide on your preferred meter location and where applicable, make quotation fee payment in order to progress application.

  • Site visit

    We’ll meet you on-site as soon as possible to discuss your requirements and book in a date for the works.

  • Receive quote and make payment

    You will have up to 90 days to send in your signed acceptance and pay for the works. We will contact you to agree a start date when the connection cost and acceptance is received.

  • Planning works

    On average, it takes 6-8 weeks from payment to carry out your works.

  • Site preparation

    We will give you a call the week before works are due to start to make sure everything is ready.

  • Works complete

    Once we’re finished, we will re-turf, re-seed any grassed areas and replant any flower beds if we’ve disturbed them.