Planning your works

Obtaining Clearance to Proceed
When a job has been design approved, you are required to submit the procedure and obtain clearance to proceed before you can carry out the work to Cadent’s network. Depending on the scope of the job, this could be a Start Date Notification (SDN), Routine Operation (RO) or Non-Routine Operation (NRO) and the table below details the criteria for each.
 
CtP Criteria Lead time Form E-mail address
SDN LP ≤63mm 3 working days SDN networkdesign@cadentgas.com
RO LP ≤12”/355mm 5 working days RO sco.networkcontrol@cadentgas.com
NRO
  • LP >12”/355mm
  • All connections into MP or IP
  • Complex works determined by the discretion of the AE*
5 working days NRO sco.networkcontrol@cadentgas.com
*Further information on determining whether an RO or NRO is required can be found in IGEM/GL/6
If your works require an easement, we will not be able to allow you to plan your works in with us until we have confirmation that the document has been signed and sealed by our legal team.
 

Safe control of operations

People who need to work on gas networks must register under the safe control
of operations (SCO) scheme.

If you have any enquiries relating to safe control of operations please contact sco.networkcontrol@cadentgas.com

Contact us


 
Escalations:

Admin and support: Laura Cheshire 07811 979680 / Jodie Cheung 07785 324556
Design & Quote: Jemima Mitchell 07827 986404 / Pete O’Neill 07785 906608
Analysis: Monir Uddin 07870 504664 / Andrew Gilfeather 07971 814627
Completions: Hannah Dakin-Stevens 07812391187 / Lee Tedds 07970 419669
 

Email us

or call us on 08453666758 opt 3