London Road, Wickford to Billericay – Upgrading aging gas pipes

    31 December 2024

    Media contacts

    Adam Murray

    mail [email protected]

    Telephone0735 037 8911

    Stephanie van Rosse

    mail [email protected]

    Telephone0776 733 7343

    • Modernising gas pipes that have been in operation for over a century
    • Upgrade will future-proof the network
    • Works will begin on 2 January for 36 weeks, ending on 8 September 

    Cadent is replacing 2.5km of gas pipes along London Road, Wickford to Billericay from 2 January to 8 September.

    The work starts from outside of number 168 London Road, Wickford along London Road to the junction with Harding’s Elms Road, Billericay.  Most of the work will be completed with temporary traffic lights, however, there will be a road closure in place in August for the junction of London Road with Harding’s Elms Road.

    Carl Williams, Head of Investment Delivery explained, “Over the years, there have been multiple repairs on these gas mains, resulting in extensive traffic management measures each time. These frequent repairs have significantly disrupted the highway and community.

    “After significant discussions with the local council and highways authority, we have developed this project to reduce the overall disruption. While this project will temporarily affect the area, it is designed to eliminate the need for recurrent repairs, thereby reducing long-term traffic congestion and disruption.

    “Ultimately, this proactive approach will enhance the reliability of our gas network and ensure that we can keep our customers safe and warm.”

    This work to upgrade ageing gas pipes will ensure the local community can continue to receive a safe and reliable gas supply into the future for many decades to come.

    The work will be carried out in six phases:

    Phase 1          2 January – 3 March

    From 168 to 312 London Road, Wickford

    Phase 2         2 January – 30 March

    From 300a London Road, Wickford to junction with Church Road, Billericay

    Phase 3        24 March - 10 April

    From junction of Church Road with London Road to Woolshots Farm, Billericay

    Phase 4         31 March – 25 April

    From 312 London Road, Wickford to Elm Farm, Crays Hill, Billericay

    Phase 5         5 May – 17 August

    From Elm Farm, Crays Hill to the junction with Harding’s Elms Road, Billericay

    Phase 6          11 August - 8 September

    London Road and Southend Road junction with Harding’s Elms Road, Billericay – Road closure at junction – diversion via Wash Road, Barleylands Road and Southend Road, A129H

    Working hours:

    To keep disruption to a minimum and get the traffic flowing back to normal as quickly as possible we’ll be working seven days a week.

    Our working hours will be Monday-Friday 8am-6pm, Saturday 8am-5pm and Sunday 10am-4pm (No noisy works will be carried out on this day.)

    Contacting Cadent about this project

    Customers with questions about this work can contact the team by:

    Phone: 0800 085 4478 – Monday to Friday 8am-8pm

    Email: [email protected]

    Cadent

    Cadent is the UK’s largest gas distribution network with a 200-year legacy.  We are in a unique position to build on strong foundations whilst encouraging the curiosity to think differently and the courage to embrace change.  Day to day we continue to operate, maintain and innovate the UK’s largest gas network, transporting gas safely and protecting people in an emergency.   Our skilled engineers and specialists remain committed to the communities we serve, working day and night to ensure gas reaches 11 million homes from Cumbria to North London and the Welsh Borders to East Anglia, to keep your energy flowing.

    Future of Gas:

    Here at Cadent we support the Government’s plans to reach Net Zero by 2050. That means we’re backing the introduction of hydrogen as a low carbon alternative to natural gas for the future. We know people love the controllability of gas and, with our network already in place, it makes sense to switch to the lower carbon alternative offered by hydrogen, which we believe can keep homes and businesses warm for generations to come.

    Cadent manages the national gas emergency service free phone line on behalf of the gas industry - 0800 111 999*

    Cadent Gas Ltd is owned by a consortium of global investors.

    *All calls are recorded and may be monitored.

    Incident alert
    0!

    Incidents

    Phone

    Smell Gas?

    0800 111 999*

    Aa Accessibility